TASK
Building a wind farm brings many challenges. One of them is transporting windmill elements. The investor was looking fWhen building a wind farm, you will be faced with many challenges. One of them is transporting windmill elements. The investor was looking for a quick and practical way to harden the surface leading directly to the construction site which is far away from the communication infrastructure.
SOLUTION
The use of ROAD SYSTEM plates was an ideal solution in this situation. Compared to traditional methods of building temporary access roads, which are not only time-consuming, but also costly, ROAD SYSTEM plates gain the advantage that they can be used many times. Their assembly and disassembly is very easy, and no special equipment is needed for transport and unloading.
RESULT
The temporary access road and the storage site for the components for the wind farm were completed in a short time. With the road plates, made of 100% recycled material, the entire investment is twice as ecological.