TASK

With the development of the production plant, it was necessary to create internal roads for trucks. A solution was sought, the installation of which did not require preparation of the base and that would allow for temporary passage of vehicles to the loading places.

SOLUTION

It was possible to lay the ROAD SYSTEM road plates directly on the ground as the ground was hard and permeable. After leveling the surface, the plates were quickly installed thanks to the special design of ROAD SYSTEM LINK.

RESULT

The road was laid in a classic way by joining the plates along the width of the strip with their longer sides, thus obtaining 3.6 m. Truck passed smoothly keeping the speed limit of 10 km/h.

USED PRODUCTS
ROAD SYSTEM 200